PROJECT WORK PLAN |
PROJECT
ACTIVITIES |
03/ 2003 |
04/ 2003 |
05/ 2003 |
06/ 2003 |
07/ 2003 |
08/ 2003 |
09/ 2003 |
10/ 2003 |
11/ 2003 |
12/ 2003 |
01/ 2004 |
02/ 2004 |
03/ 2004 |
04/ 2004 |
Phase 1:
Project Start up |
Applicable for all grants |
Preparation for Grantee
Orientation (book flight & accommodation, make presentation on project) |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
Participation in Grantee
Orientation |
X |
|
|
|
|
|
|
|
|
|
|
|
|
|
Receive first installment from
World Bank |
|
X |
|
|
|
|
|
|
|
|
|
|
|
|
Procure goods, works and
services for the project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prepare Progress Report for
MSGP Staff |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Phase 2:
Project Implementation |
Applicable for all grants |
Matching contribution for the
second phase of project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Receive second installment
from World Bank |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prepare Second Progress Report
for MSGP Staff |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
5 Phase
3: Project Implementation |
Applicable only for grants over 25K |
Matching contribution for the
third phase of project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Receive third installment from
World Bank |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Prepare third Progress Report
for MSGP Staff |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Phase 4:
Project Implementation |
Applicable only for grants over 50K |
| Matching contribution for the
forth phase of project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Receive fourth installment from
World Bank |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Task 10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Task 11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Task 12 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Prepare fourth Progress Report
for MSGP Staff |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Last Phase:
Project Evaluation |
Applicable for all grants |
| Matching contribution for the
final phase of project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Check outcomes against indicators |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Evaluate results and impact of
the project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Ensure sustainability and/or
follow up of the project |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Prepare Final Report to MSGP
Staff |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Disbursement contingent on
receipt of satisfactory final report |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Receive final installment from
World Bank |
|
|
|
|
|
|
|
|
|
|
|
|
|
|