General Information. Activities

Output

Activity

Tasks

Implementation

Inputs

Timing

Notes

Caspian Regional Thematic Centre for Integrated Transboundary Coastal Area Management Planning Act. IB.1-3

Establishment and operation of the ITCAMP-CRTC . Contribute to the region-wide initiatives of the CEP

Establish ITCAMP Centre in I.R.Iran including identification of personnel, setting up office, provision of equipment Govt, Director Consultant, UNDP/PCU, Admin

Equipment

Jun 1999

Completed
Establish Caspian ITCAMP Working Group comprised of contact points nominated by the Governments All Govts, Director Admin

Jun 1999

Completed
Establish ITCAMP National Networks through the ITCAMP Contact Point for each country NFPs, CPs, Director Admin

Equipment

Jun 1999

Completed
Create a functioning communication and information exchange system linking the CRTC with the 4 Contact Points, the Consultant, the PCU and the Iranian NFP and ISCF PCU, CRTC, CPs Admin

Equipment

Jun-Jul 1999

Partially completed

Provide close linkages to the TDA activities by collating and contributing data and information on ITCAMP

Director, CRTC,

Data & Info CRTC

Admin

Through-

out

Continuing activity

Coordinate ITCAMP input to the NSAPs and SAP by identifying regional and common issues

Director, CRTC, PCU Admin

Through-

out

Continuing activity

Establish and maintain close cooperation with other CRTCs and in particular, with Water Level Fluctuation CRTC to address immediate threats to health, safety and the environment posed by sea level fluctuations

Director, CRTC, all other CRTCs Admin

Through-

out

Continuing activity

Act as a regional focal point for all ITCAMP and related activities within the CEP

Director, CRTC Admin

Through
-out

Continuing activity
A series of national Coastal Profiles, a regional Overview of Coastal Planning and Management in the Caspian Region and an ITCAMP Training Course in each participating country Act. VC.1

Assessment of the ITCAMP situation in each participating country leading to a regional overview

Develop a draft structure and contents for the Coastal Profiles and adopt after taking into account country comments Director, Consultant, CPs Workshop

Aug/Sep 1999

Completed

First Meeting of the ITCAMP Working Group to discuss : Draft Work Plan, Coastal Profiles, Reviews of national coastal legislation and planning procedures; possibility of pilot projects

Director, CRTC, CPs, Consultant Workshop

Oct 1999

Completed

Review National Reports produced for TDA Framework; liaise with other CRTCs and rationalize any overlap and/or duplication

Consultant, Director Mission and homebased

Jun-Jul 2000

Delayed – pre-requisite for Coastal Profiles

Liaise with other CRTCs as appropriate and access, obtain and review existing data sets, evaluate comprehensiveness and reliability of data, identify gaps in essential information and undertake necessary field work for essential new data to remedy gaps

CPs, NPPPs,

Data & Info CRTC, other CRTCs

Director;

Country sub-contracts

Jul-Aug

2000

Delayed – must precede Coastal Profiles

Compilation of the Coastal Profile: review national legislation for coastal area planning, management, and resource use; evaluate national responsibilities for ITCAMP at the national, provincial, and municipal levels; collate with other descriptive data and information, and maps, etc

CPs, NPPPs,

Data & Info CRTC

Country sub-contract

Aug-Oct

2000

Delayed. To be preceded by review of Natl Reports & discussion with other CRTC

Based on the 5 National Coastal Profiles, and the preparation of coastal maps, produce a Caspian Regional Coastal Profile comprising an identification of regional issues, institutional strengths and weaknesses, capabilities, training needs and training opportunities for the Caspian Region

Consultant, Director Admin

Publication

Oct

2000

Home-based – communicate electronically

Organize and deliver a basic training course in ITCAMP principles and procedures, as well as the technical, institutional and other ingredients required for effective coastal planning, in each of the participating countries

Director, Consultant, IOC Admin

Oct-Dec

2000

Requires firm scheduling – logistics and organization
Draft Guidelines for the ITCAMP Process, tested and evaluated in the field through pilot-scale trials Act. VC.2

Development of Guidelines for ITCAMP and Field evaluation of draft Guidelines through Pilot Projects

 

Develop draft Guidelines for Integrated Coastal Area Management Planning which will be broad enough to be applicable to the circumstances of each of the participating countries as identified in the National Coastal Profiles

Consultant, Directror Admin

Jan

2001

Home-based – communicate electronically

Develop selection criteria for ITCAMP Pilot Projects, identify potential funding support, for ITCAMP Pilot Projects

Director, CRTC, Consultant Admin

Jan

2001

Home-based – communicate electronically

Second ITCAMP Working Group Meeting to review the Regional Overview and its contribution to the TDA; review the draft Guidelines for Integrated Coastal Area Management Planning; and identify the site in each country for ITCAMP Pilot Projects

Director, CRTC, Consultant, CPs Admin

Mission

Workshop

Feb

2001

 

Commence work on the Pilots by establishing an interim Coastal Planning Office and Planning Team in each locality where a Pilot Project is to be undertaken

Govt, CPs, NPPPs Pilot

Co-funding

Mar

2001

Expected to be undertaken with co-funding support primarily from Govts.

Maybe only 1-2 pilots.

Consultant’s and Director’s input from homebase electronically, however, may require field mission

For each pilot site, determine the objectives of the Coastal Area Management Plan within the Government’s social, economic and environmental policies Govt, CPs, NPPPs Pilot

Co-funding

Mar

2001

Undertake socio-economic and ecological surveys; assemble the results of database searches; obtain available maps and develop required maps CPs, NPPPs,

Director

Pilot

Co-funding

Apr-Jul

2001

Identify the existing and potential problems and opportunities for resource use, economic development, human well-being and environmental protection within the selected area

CPs, NPPPs,

Director, Consultant

Pilot

Co-funding

Apr-Jul

2001

Using the data and maps and reflecting Central Government planning policies, produce a draft Coastal Management Plan comprising overall policies and objectives, standards, limits, zones, sensitive coastal areas, and other guidance for coastal managers

NPPPs,

Director, Consultant

Pilot

Co-funding

Aug

2001

Publish the Draft Coastal Management Plan and undertake a process of consultation with stakeholders through public meetings, media campaigns, and other mechanisms, to obtain scientific, technical, NGO, social, local government, industrial, public and any other views

NPPPs,

Director,

Consultant

Pilot

Co-funding

Publication

Sep-Oct

2001

Taking into account the input received, recalling the original objectives, and reflecting Government planning policies, finalize the Coastal Management Plan and adopt it as the operational plan for the pilot locality

NPPPs,

Director,

Consultant

Pilot

Co-funding

Nov

2001

Evaluate each Pilot Project, identifying strengths and weaknesses and noting how the Integrated Coastal Area Management Planning Process can be improved to be more effective in the Caspian situation and reflect the needs of Caspian countries

CPs, Director, Consultant Admin

Mission and

Homebased

Dec 2001

-Jan 2002

Field mission to be followed by electronic communications
Published Handbook for ITCAMP in the Caspian environment Act. VC.3

Production of the Handbook for ITCAMP

Based on the Draft Guidelines, produce a draft Handbook for Integrated Coastal Area Management Planning for the Caspian Coast reflecting the Caspian Regional Coastal Profile and the experience gained from the Pilot Projects

Consultant, Director Admin

Dec 2001

-Jan 2002

Home-based – communicate electronically

Third ITCAMP Working Group Meeting to review the results of the Pilot Projects, adopt the draft Handbook and endorse the material which is to be contributed to the SAP

CRTC, Director, CPs, Consultant Workshop

Admin

Mission

Feb

2002

Final Workshop

Final editing, translation, layout and design, printing, publication and distribution of the Handbook for Integrated Coastal Area Management Planning for the Caspian Coast

Director, Consultant, Sub-Contractors Admin

Publication

Mar-Sep

2002

Home-based – communicate electronically
Scope and prescription for Caspian Atlas of Coastal Resources Plan for Caspian Atlas of Coastal Resources

In cooperation with the PCU and other CRTCs, in particular the Data & Info CRTC, the Water Fluctuation CRTC, Desertification CRTC and Emergency Response CRTC, develop the conceptual and technical specifications for the Caspian Atlas of Coastal Resources, negotiate for the necessary co-funding support for the publication of one or more volumes

PCU, Consultant, Director, CPs,

Data & Info CRTC

Admin

Homebased

Aug-Sep

2002

Home-based – communicate electronically

Introduction

Objectives

Activities

Time-table

Relation with
other CRTCs

BackHomeSearchSite mapE-mail

The ITCAMP Network | Publications and Activities | Useful Links | Reading Room
     

Home

CRTC for Integrated Transboundary Coastal Area Management and Planning
Department of Environment, Marine Environment Research Bureau
187, Nejatollahi St, PO Box 15875-5181, Tehran, Islamic Republic of Iran
Tel.: +9821 8808776; 8901096
Fax: +9821 8907223; 8901269
E-mail: cep-doe@neda.net
© 2001-2003, CEP